Acting as the general contractor, ºì˹µÆÓ°Ïñ constructed a bridge widening project and acceleration lane to enhance safety and mobility for travelers merging onto southbound I-15 from Promontory Road in Brigham City, UT.

The project consisted of the following deliverables:

– Demolition of 12’ of the existing bridge deck, parapet, abutments & approach.

– Installation of new two bents with piling, 2 – 235’ steel girders, parapet, 34’ deck, abutments, and joints.

– Pothole patch existing deck.

– 2900 CY of cellular concrete fill.

– 7000 CY of import borrow.

– New concrete constant slope barrier, guardrail & cable barriers.

– Asphalt paving new profile – south of bridge & widening pavement section.

– Polyester & thin bonded polymer overlays.

– Concrete slope protection.

date

October 2022

location

Brigham City, UT

client

The Utah Department of Transportation ()

Take the next step

Interested in working with ºì˹µÆÓ°Ïñ? Let us help you get started on your project. Contact us to find out more information or to request a bid.

Get in touch